Dismantling works begin on collapsed Baltimore bridge
02 April 2024
Video Copyright: EYEPRESS
Teams of engineers have begun the intricate process of cutting and lifting the first section of the collapsed Francis Scott Key Bridge, which crumpled into the Patapsco River last week after a Singapore-flagged Dali cargo ship crashed into one of its supports.
A recovery team led by the US Coast Guard and the state of Maryland aims to quickly reopen the port, the largest in the US for “roll-on, roll-off” vehicle imports and exports of farm and construction equipment.
But first it must free the cargo vessel Dali, stuck under steel bridge debris with 4,000 containers and a 21-member crew stranded aboard since the accident.
To illustrate the task ahead, officials said recovery workers needed 10 hours to cut free and remove a 200-ton piece of debris - what they called “a relatively small lift.”
“We’re talking about something that is almost the size of the Statue of Liberty,” Governor Wes Moore told a news conference.
“The scale of this project, to be clear, is enormous. And even the smallest [of tasks] are huge.”
Beneath the surface, the job is even more complicated than originally imagined, said US Coast Guard Rear Admiral Shannon Gilreath, as the twisted steel is obscured by murky waters darkened by the volume of debris.
“These girders are essentially tangled together, intertwined, making it very difficult to figure out where you need to potentially cut so that we can make that into more manageable sizes to lift them from the water,” Gilreath told the same news conference.
Officials declined to estimate how long it would take to clear the harbor.
Limited ship traffic resumed for the first time on Monday after recovery teams opened a temporary channel with a controlling depth of 11 ft (3.35 meters) on the northbound side of the wreckage.
The first vessel to transit the channel was a tugboat pushing a barge supplying jet fuel to the US Department of Defense, the Coast Guard said on Facebook, posting video of the barge sliding beneath a truncated section of bridge that is still standing.
A second temporary channel on the southbound side with a depth of 15 to 16 ft (4.6 to 4.9 m) would open “in the coming days,” Moore said.
Once debris is cleared, a third channel with a depth of 20 to 25 ft (6.1 to 7.6 m) would allow almost all tug and barge traffic in and out of the port, Gilreath said.
US President Joe Biden will get a first-hand look at the recovery on Friday when he travels to Baltimore, White House spokesperson Karine Jean-Pierre said.
The Biden administration has helped secure barges and a crane along with an early influx of money and was working with Congress to ensure the federal government pays to rebuild the bridge.
(Reporting by Daniel Trotta in Carlsbad, California; Additional reporting by Steve Holland and Jarrett Renshaw in Washington; Editing by Aurora Ellis and Stephen Coates)