Award-Shortlisted Demolition: Bringing Down the Former Kmart Headquarters
26 February 2025
Shortlisted for in the Environmental and Recycling category at the 2024 World Demolition Awards, the demolition of the former Kmart Headquarters in Troy, Michigan, was no ordinary teardown. Adamo Demolition took on the challenge of dismantling the 131,900-square-yard (110,290-square-metre) site with precision and sustainability at its core, achieving a remarkable 97.37% recycling rate, setting a high standard for large-scale urban demolitions.
Between September 2023 and June 2024, Adamo Demolition Company carried out the task of dismantling the former Kmart Headquarters in Troy, Michigan—a once-bustling corporate hub that sprawled a site covering 131,900 square yards (110,290 square metres).
Situated next to one of Metro Detroit’s busiest shopping centres, the US$3 million (€2.8 million) project required meticulous planning to ensure the work progressed smoothly while minimising disruption.
Challenges and Planning
This was no straightforward demolition. The headquarters consisted of multiple interconnected buildings, linked by elevated corridors, which demanded careful sequencing to avoid uncontrolled collapses. Moreover, with the site’s proximity to a major commercial hub, logistics became a critical aspect of the operation.
Adamo Demolition devised a phased approach, ensuring that equipment and materials were moved efficiently while keeping disruption to neighbouring businesses to a minimum.
Weather conditions presented an additional challenge, requiring flexible scheduling to maintain progress without compromising safety.
With demolition projects of this scale, timing is everything—working around adverse conditions while ensuring the structural integrity of remaining sections demanded constant assessment and adjustment.

Dismantling and Recycling
Bringing down the buildings required a fleet of high-reach excavators, including the CAT 390, CAT 374, and Volvo 380.
The interconnected nature of the structures meant that sections had to be carefully deconstructed in stages, ensuring stability throughout.
Each phase of demolition was monitored in real time using drone surveys and site cameras, allowing for ongoing assessment and efficient decision-making.
Adamo Demolition’s commitment to recycling played a key role in the project. An impressive 97.37% of the materials removed from the site were recycled. Concrete debris was processed into reusable aggregate, while steel components were systematically dismantled and sent for recycling.
A significant 48,977 tons (44,400 tonnes) of hard-fill materials were diverted from landfill, repurposed for roadway construction. Additional materials, including insulation and electrical components, were recovered and redirected to appropriate recycling channels, maximising the reuse potential of the demolition waste.
Safety and Environmental Considerations
Ensuring safety was a top priority, with no health or safety incidents reported throughout the project. Dust suppression measures, including misting systems, helped to control airborne particles, while noise barriers reduced disruption to the surrounding area.
Given the presence of hazardous materials, including asbestos, strict compliance with environmental regulations was essential. Trained specialists handled the identification and removal of these materials, ensuring that disposal was carried out safely and responsibly.
A structured training programme prepared workers for the unique challenges of this site, reinforcing best practices and risk mitigation strategies.
Daily safety briefings provided updates on changing conditions and ensured that all personnel remained aware of potential hazards.
Coordination with local authorities also played a key role in streamlining emergency response protocols and maintaining compliance with all regulatory requirements.
Beyond physical safety measures, environmental impact monitoring was a continuous effort. Air quality tests were conducted regularly to ensure compliance with health and environmental standards, particularly given the site’s urban setting.
The implementation of both manual and mechanical sorting processes ensured that recyclable materials were separated efficiently, significantly reducing the amount of waste sent to landfill.
Completion and Legacy
By June 2024, the former Kmart Headquarters had been successfully dismantled, with the site cleared and prepared for its next phase of development. The focus on material recovery meant that much of the structure was not simply discarded but given a second life in new construction projects.
Throughout the process, coordination with environmental regulators, city officials, and recycling partners ensured that the demolition met all necessary standards. Effective communication and adaptive project management were key to avoiding unforeseen delays and keeping the workflow efficient from start to finish.
This project highlights the complexity of large-scale urban demolitions, particularly in high-traffic environments. The methodologies applied here provide a useful reference for future demolitions that require extensive recycling and waste management planning.
With careful execution, strong safety measures, and a commitment to sustainability, the former Kmart Headquarters project serves as a case study in balancing efficiency with environmental responsibility.